SM06-GEO-PC7

Budapest Public Utilities Ltd. is using geothermal energy to green the district heating in Zugló with the grant from the Swiss Contribution.
Increasing the exploitation of the geothermal well established at Fehér street site of BKV Railway Vehicle Repair and Service Ltd. by utilising heat in the district heating network of Zugló
Welcome to our website!
In the framework of the SM06-GEO programme „Geothermal energy resources for district heating", Budapest Public Utilities Ltd. as the applicant and Association of Hungarian District Heating Enterprises (hereinafter referred to as MaTáSzSz) as the civil organisation successfully submitted an application under the title „Increasing the exploitation of the geothermal well established at Fehér street site of BKV Railway Vehicle Repair and Service Ltd. by utilising heat in the district heating network of Zugló".
The amount of the grant awarded for the programme component SM06-GEO-PC7 is
803 692 018 HUF
The project was supported by the Swiss Contribution with the national co-financing of the Hungarian Government.
Project objectives and description
The main goal of the programme component (tender) is to further improve the greening, efficiency and sustainability of district heating services provided by Budapest Public Utilities Ltd. by integrating geothermal energy into district heating.
Within the framework of the project, by Budapest Public Utilities Ltd. will increase the utilisation of the geothermal well previously established at the Fehér Street site of BKV Railway Vehicle Repair and Service Ltd. by connecting the geothermal energy source to the district heating district of Zugló.
The reduced emissions of air pollutants will improve the air quality of the affected area, and the greenhouse gas emissions avoided will contribute to global climate protection. The integration of geothermal energy into the district heating will provide broad access to renewable energy, contributing to sustainable economic growth.
The following main professional activities will be developed under the programme component:
· Design and construction of the district heating network;
· Design and construction of the thermal water heat exchanger;
· Implementation of the control system;
· Implementation of the connection to the heat supply system of the well site.
The result of the developments
Increase in geothermal energy production as a result of the activity compared to the baseline before the start of the activity: 31 898 GJ/year.
The annual greenhouse gas emission reduction will be 1 239 tonnes of CO2.
Dates
Date of conclusion of the grant agreement: 04 March 2025
Start date of project activities: 01 January 2025
Planned project closure date: 31 May 2027
Events
Project launch event: 14 May 2025 11:15 AM
Press room
Press contact details: sajto@budapestikozmuvek.hu
Documents
Contact
Budapest Public Utilities Ltd.
- Postal Address: 1519 Budapest, P.O.B. 454
- Phone:+36 1 700 7000; Fax:+36 1 206 1545
- info@budapestikozmuvek.hu
- www.budapestikozmuvek.hu
Photos of the project



Project launch event: 14 May 2025